How to Build Scaffolding
- 1). Place the inside sills or pads on the ground next to the face of the building; use pads in the case of uneven ground. Set inside uprights at each end of the building and toenail them to the sill. Use a carpenter's level and plumb the uprights. Next, tie the uprights to the building using wood cleats.
- 2). Nail a one-by-six ribbon board to the uprights at three and one half inches below the plank height. Layout and nail intermediate uprights in place along face of wall. Uprights should not be spread out more than 10 feet.
- 3). Lay the outside sill or pads on the ground. Set up two outside uprights and nail in place. Level and nail ledger boards connecting the inside and outside uprights; all ledger boards will be resting on top of the ribbon boards. The ledgers should be at the height of where the walking planks will be placed. Place ribbon board below outside ledger and nail.
- 4). Place outside uprights opposite of the inside uprights and nail them into place. Next, connect each outside upright with the inside upright using ledger boards. Use a level to make sure ledgers are level before nailing.
- 5). Place walking planks for a platform on top of ledgers; the planks should run over the ledgers at least 12 inches on both sides. Nail second-level ribbons and ledgers in place at height of next work area. Next, nail diagonal braces to outside uprights to provide lateral support. Place the next work level planks on the ledgers.
- 6). Nail the guardrail into place; the guardrail should be installed around 42 inches height-wise. The mid-rail will be placed around 28 inches. In some cases, there may be a need for a toe board; this type of board protects people from falling objects that get kicked off of the scaffolding. The toe board will be nailed against the planks of the scaffold walk way.